By Adedapo Adesanya

The Nigerian National Petroleum Corporation (NNPC) and First Exploration and Petroleum Development Company (First E&P) Joint Venture has announced the commencement of oil production from the Anyala West field in Oil Mining Leases (OMLs) 83 and 85.

Located in the shallow waters offshore Bayelsa State, First E&P will operate the two blocks on behalf of the national oil company and company’s Joint Venture.

According to the firms in a statement, the Anyala – Madu field development project objective is to develop 142 million barrels of oil and 98 billion standard cubic feet of gas from the fields in Phase 1.

“It utilises the Abigail-Joseph FPSO, a 274 meters long converted Suezmax trading tanker with a storage capacity of 700,000 barrel, oil processing capacity of 60,000 barrels of oil per day, produced water treatment of 20,000 barrels per day and a gas handling capacity of 39 million standard cubic feet per day.

“A total of seven development wells have been planned in Phase 1 and approved by the Department of Petroleum Resources (DPR) in the Anyala West field (OML 83) which will be developed along with the nearby Madu field in (OML 85) to be jointly produced in the Abigail-Joseph FPSO,” the statement said.

They noted that each field is being developed with an unmanned conductor supported platform (CSP), a novel drilling and development technology deployed in the Niger Delta.

“The FPSO underwent upgrade, refurbishment and life extension works in Keppel Shipyard, Singapore, to meet specified standards and specifications and the excellent partnership between NNPC, First E&P, Yinson and Keppel Shipyard, helped to ensure these critical pre-deployment activities for the FPSO were completed in record time.

“A team of young Nigerian professionals including 7 NNPC staff were part of the successful extension works in the Keppel Shipyard and they will form an integral part of the FPSO operations team in the production phase.

“The project at its peak production will produce about 60,000 barrels of oil per day, unlock over 300 million barrels of crude oil recoverable reserves and create value of over $8 billion for the Federal Government of Nigeria over the total lifespan of all phases of the project.

“The project was carried out with over 2.5 million man-hours with zero Lost Time Injury,” it stated.

Speaking on the partnership, the Group Managing Director, NNPC, Mr Mele Kyari, described the project as a milestone for Nigeria being the first wholly indigenously executed and funded integrated oil and gas project in the shallow offshore.

“This a project that will go a long way in helping us to achieve our strategic objective of three million barrels of oil per day by 2023.

“This is the first project that NNPC, as a JV partner, will carry its partner to provide funding on behalf of the Joint Venture. It is a signal of hope for our country that there is indeed light at the end of the tunnel. The accomplishment of this great feat in the midst of a pandemic is a clear demonstration of our resolve to achieve performance excellence in spite of all odds,” he said.

In his remarks, Managing Director of First E&P, Mr Ademola Adeyemi-Bero, said, “We appreciate all the support that was given to us by the NNPC, the Department of Petroleum Resources, Nigeria Content Development Monitoring Board (NCDMB) as well as the hard work and collaboration by First E&P staff, our contractors as well as Nigerian banks in the achievement of this major milestone.”

By Adedapo Adesanya

Adedapo Adesanya is a journalist, polymath, and connoisseur of everything art. When he is not writing, he has his nose buried in one of the many books or articles he has bookmarked or simply listening to good music with a bottle of beer or wine. He supports the greatest club in the world, Manchester United F.C.