Excitement as NNPC Flags Off 50MW Gas Power Plant in Maiduguri

October 4, 2021
Gas Power Plant

By Adedapo Adesanya

The federal government through the Nigerian National Petroleum Corporation (NNPC) has flagged off the construction of a 50 megawatts gas power plant which upon completion would supply electricity to Maiduguri and environs.

Approved by President Muhammadu Buhari, the emergency power project followed the sustained attack on power supply lines (330 KVA and 132 KVA lines) from the national grid to Maiduguri, Borno State, by suspected terrorists which have put the city and environs in total blackout for the past nine months.

The project would be executed by the NNPC in collaboration with Chinese and American firms.

In August 2021, Business Post had reported that NNPC signed an official contract with China Machinery and Engineering Corporation, CMEC and General Electric, GE for the construction of the project.

The corporation stated that the groundbreaking ceremony last Thursday signified the official commencement of the project as the contractors had since moved to the site.

Speaking at the occasion, the Group Managing Director of NNPC, Mr Mele Kyari, gave the assurance that the project would be delivered in good time and has already awarded the contract to General Electric Global for the supply of gas turbine.

Mr Kyari said orders have already been placed for the turbine and other facilities for the project.

While performing the groundbreaking ceremony in Maiduguri, the Governor of Borno State, Mr Babagana Zulum, said that the project would bring significant relief to the people of Borno state and expressed gratitude to the federal government under the leadership of President Buhari for approving the construction of 50 megawatts power plant which is the first of its kind in the history of the country.

He said the plant would impact positively on socio-economic activities of the state which has been crippled by the destruction of electricity towers by the insurgents.

He assured residents of the commitment of his administration to work with all stakeholders to ensure the successful completion of the project in the stipulated six months time frame.

He expressed the appreciation of the government and people of Borno to Mr Buhari and NNPC for the sustained concern and support to the people of Borno.

Adedapo Adesanya

Adedapo Adesanya is a journalist, polymath, and connoisseur of everything art. When he is not writing, he has his nose buried in one of the many books or articles he has bookmarked or simply listening to good music with a bottle of beer or wine. He supports the greatest club in the world, Manchester United F.C.

Leave a Reply

World Bank
Previous Story

Nigeria Gets $400m from World Bank for COVID-19

SERAP
Next Story

SERAP Rejects Buhari’s Conditions for Lifting Twitter Ban

Latest from General